What does REB 23.003 govern?

REB 23.003 is the German rule for formula-based quantity determination in construction. It sets out which formulas quantities are calculated with from take-off data – and in what form that calculation is documented.

Its practical core is not the mathematics. It is traceability: on a public contract a quantity is not a number but a claim that has to be evidenced. REB prescribes what that evidence looks like.

Why the calculation matters more than the result

Anyone who can only produce the final total at an audit ends up in a discussion. Anyone who can show the formula with its input values is finished.

An example: an area of 128.50 m² can come from a rectangle, from several part-areas with deductions, or from a station take-off. The result is identical, the evidential value is not. The auditor wants to see how you arrived at the figure – particularly where recesses were deducted.

Which is why the decisive question to put to any software is not “does it calculate REB?” but “does the calculation stay attached to the item?”.

The common formulas

REB 23.003 contains a whole series of formulas. In road construction and Tiefbau you mainly meet these in daily work:

ApplicationWhat for
Rectangular and triangular areaspatches, part-areas, simple break-ups
Areas with deductionspaved areas with recesses, manholes, tree pits
Station take-offcarriageways, trenches – area and volume across stations
Body calculationsexcavation, backfill, frost protection layer

The station take-off is the most important form in civil engineering: widths or cross-sections are recorded at regular intervals (stations) along an axis, and area and volume follow from them. For a trench or a carriageway that is the natural way to measure.

A worked example

Take a carriageway area recorded at three stations:

StationWidth
0+0003.10 m
0+0203.40 m
0+0403.20 m

Between two stations the area is formed from the mean width and the spacing:

  • Section 1: (3.10 + 3.40) ÷ 2 × 20 = 65.00 m²
  • Section 2: (3.40 + 3.20) ÷ 2 × 20 = 66.00 m²
  • Total: 131.00 m²

These three lines are precisely the evidence. They stand like this – with stations, widths and subtotals – on the take-off sheet, and they have to do so in the system too.

From sheet to system: DA11 and X31

Take-off data is exchanged between programs through two formats:

FormatPurpose
DA11take-off data in the classic GAEB data exchange
X31the same job in the XML version

It becomes relevant as soon as a design office, a surveyor or the client processes the data further. Anyone calculating purely internally manages without – anyone doing Straßenbau for public clients tends not to.

The step everybody underestimates: the input

Every take-off program calculates reliably once someone has entered the values. That is exactly where the effort sits: a crew leader measures on the road and writes on paper; in the office somebody types the same figures a second time.

That second pass is not only time, it is also the most common source of error. A transposed digit while typing is invisible – the formula calculates with it without complaint.

How to avoid the typing without giving up the paper is described in Digitising handwritten site sheets .

What makes a good take-off sheet

Independently of any software:

  1. List stations or part-areas individually, not just the total.
  2. Name the deductions, do not merely deduct them – “less manhole 1.20 × 1.20”.
  3. Date and signature, because the sheet is the evidence.
  4. Item number from the contract, not your internal one.
  5. One sheet per call-off or construction section, so the assignment stays unambiguous.

These five points decide more about a smooth audit than the choice of program does.

Frequently asked

Do I have to know the formulas by heart? No. You have to be able to recognise whether the formula applied fits the situation – and for that it has to be visible.

What if we calculate differently from the program? Then you correct it. A calculation you cannot change is not a calculation, it is a result.

Does REB apply to very small quantities too? For a patch of three square metres the simple area is as a rule enough. Formula-based determination becomes mandatory where the contract provides for it – a look at the contract conditions is worth it.

Where do I find the rule in full? The REB procedural descriptions are issued through the responsible federal and state bodies. For daily work the implementation in the program is usually enough – for a dispute the wording should be to hand.

Second example: excavation across stations

Areas are the easy case. In Tiefbau it is mostly about volume, and there the benefit of the station take-off shows more clearly.

A pipe trench recorded at four stations. Width and depth are written down:

StationWidthDepthCross-section
0+0000.80 m1.40 m1.12 m²
0+0150.80 m1.60 m1.28 m²
0+0300.80 m1.75 m1.40 m²
0+0450.80 m1.55 m1.24 m²

Between two stations the mean of the two cross-sections is formed and multiplied by the spacing:

  • Section 1: (1.12 + 1.28) ÷ 2 × 15 = 18.00 m³
  • Section 2: (1.28 + 1.40) ÷ 2 × 15 = 20.10 m³
  • Section 3: (1.40 + 1.24) ÷ 2 × 15 = 19.80 m³
  • Total: 57.90 m³

The value of this breakdown lies not in the result but in the fact that every intermediate line is checkable. If a depth is questioned, that concerns one section – not the whole quantity.

Anatomy of a take-off sheet fit for checking

Whether you work on paper or digitally, the same entries belong on the sheet:

AreaContentWhy
Headerclient, contract, call-off, dateWithout assignment the quantity is worthless
Headeritem number from the contract bill of quantitiesThe language of the audit
Linesstations or part-areas individuallyCheckability per section
Linesdeductions named, not merely deducted“less manhole 1.20 × 1.20”
Footersubtotals and final quantityTraceability of the addition
Footername and signatureThe evidential character

The most common shortcoming is the fourth point. A deduction without a description looks like an arithmetic error at the audit, and clearing it up costs more time than the description would have.

DA11 and X31 in practice

The data exchange sounds more technical than it is. Two situations where it is genuinely needed:

A design office has surveyed. The take-off data arrives as a DA11 or X31 file and has to go into your billing. Without an interface you retype the stations – with everything that means in terms of errors.

The client demands the take-off data. Some authorities want not only the invoice but the take-off file, so they can recalculate it in their own system. Then the format is not a convenience but a precondition.

If neither case occurs with you, you do not need the interface – and should not pay for it either. If in doubt, ask your largest client before you select on that basis.

Common calculation errors

ErrorHow it arisesHow it is noticed
Part-area captured twicetwo sheets for the same sectionquantity exceeds the area on the ground
Forgotten deductionmanhole or tree pit overlookedauditor measures it again
Wrong unitm² instead of m³ for excavationthe amount is out by orders of magnitude
Stations mixed uprecorded in the wrong orderimplausible progression of the cross-sections
Transposed digit while typingsecond capture in the officeas a rule not noticed at all

The last one is the most expensive, precisely because it stays invisible. A transposition downwards is never objected to by the client.

Joint take-off with the client

The VOB knows the joint take-off: client and contractor establish the quantities together. Where it is agreed, you should insist on it – it is the most effective protection against later discussions.

What a joint take-off means in practice:

StepWhoResult
Arrange the appointmentyouin good time before the work is covered up
Measure togetherbotheach side with its own notes
Sign the sheetbothquantity established by agreement
Note discrepanciesbothname the disputed points instead of glossing over them

The second point is why this belongs here: work that will no longer be visible later has to be measured before it is covered. A backfilled trench cannot be re-measured. Anyone who misses the appointment depends on their own Zettel – and on the client accepting it.

If no joint take-off comes about, the rule is: measure, document, photograph, send the result. A take-off that has gone unchallenged is worth considerably more than a figure that first appears with the invoice.

In summary

REB 23.003 is less a calculation rule than an evidence rule. The formulas are craft; the value lies in the calculation being open to inspection. Anyone capturing take-off digitally should therefore first check whether the calculation is preserved – and only afterwards how fast the input is.